| Klamath Falls Campus : Construction Schedule | |||
---|---|---|---|---|
Anticipated Project Timeline | Project Name | Project Location | Anticipated Impacts | Other/Notes |
April 15, 2024- August 29, 2025 | New Student Housing | Area between Arboretum and CU. (Tennis Court Area) | Permanent closure/removal of the tennis courts | Early work: 4/15/2024-6/7/2024 Construction: 6/10/2024-8/29/2025 |
June 17, 2024- August 30, 2024 | Boivin Traffic Improvements | Industrial Park Drive | Lot E and Industrial Park Drive will be closed/inaccessible for duration of project. | Deliveries via Campus Dr to East & North University Drive |
May 20, 2024- April 25, 2025 | Geothermal Phase 1 Building Renovation | Southeast corner of campus. (Geothermal Heat Exchange Building) | There will be planned geothermal shutdowns which could temporarily affect access to hot water. | |
June 17, 2024- August 30, 2024 | Geothermal Phase 2 Distribution Piping | Campus wide. Some access restrictions to Lot B. | There will be planned geothermal shutdowns which could temporarily affect access to hot water. | |
June 3, 2024- December 27, 2024 | ABA Clinic Renovation | 200 Commercial Street | No impacts on Klamath Falls Campus |
*Athletics reroof may be added if funding is identified.
For more information, reach out to Facilities at 541-885-1690